COURANT PROJECT

PROGRESS AND NEXT STEPS

Milestones:

  • Design [2023]

  • Pre-FEED Study [2023]

  • Allocation of a 307 MW electricity block from Hydro-Québec [2024]

  • Submission of the Project Notice to MELCCFP [March 2025]

  • Ministerial Directive [March 2025]

  • Extension of the Environmental Evaluation Procedure (PEEIE) to include the entire project [November 2025] 

Ongoing:

  • Environmental Impact Study preparation

Upcoming Steps:

  • Submission of the Impact Study to MELCCFP

  • Public information period

  • BAPE (Bureau of Public Hearings on the Environment) Inquiry and Public Hearing

  • MELCCFP Environmental Analysis

  • BAPE report

  • Quebec Government decision

  • Start of construction work

  • Commissioning of the complex